What a Pre-Shipment Acceptance Test Should Cover

Published: 2026-06-11T00:00:00.000ZCategory: Industry Trends
Author: Chen Wei  | Experience: in the machine tool industry  | Position: Chief Engineer
What a Pre-Shipment Acceptance Test Should Cover

Why the test matters more than the test part

A demonstration part proves the machine can make that part on that day. An acceptance test proves the machine is inside a stated tolerance and will stay there after it is re-levelled on your floor. Ask for the second.

Geometric accuracy

  • Squareness of X to Y, Y to Z and X to Z, measured with a granite square and dial indicator or a laser.
  • Straightness and parallelism of each axis over full stroke, not over a 500 mm sample.
  • Spindle taper runout and spindle axis squareness to the table or ram face.

Positioning and repeatability

Laser interferometer reports per ISO 230-2, bidirectional, at increments that cover the full stroke. Look at the reversal value - backlash compensation can hide lost motion in the unidirectional figure. A report that quotes a single accuracy number without the per-axis data is not a report.

Dynamic checks

  • Ballbar circular test at 300 mm and at the largest practical radius, to expose servo mismatch and stick-slip.
  • Spindle thermal drift: cold-to-warm displacement over 2-4 hours at working speed.
  • Continuous run under load for 24-72 hours, with spindle temperature and axis following error logged.

The document package

Shipment should include: laser report per axis, geometric inspection record, ballbar plot, spindle runout record, hydraulic and lubrication pressure readings, electrical schematics, PLC and parameter backup, and the leveling procedure for re-installation.

Witnessing versus accepting paperwork

If travel is not practical, ask for the raw laser files and a video of the ballbar test with the serial number of the machine visible. Numbers without machine identity can belong to any machine in the hall. Where a witness test is possible, watch the reversal and the thermal drift - they are the two results most often absent from a clean-looking sheet.

After arrival

Re-level, re-check squareness, and repeat one laser axis before production. Foundations settle; a machine that was square in the builder's shop is not automatically square on a new floor.